As an Amazon Associate I earn from qualifying purchases. How this site is paid for

Guide

Concrete: How Much to Order, Mixing, Pouring and Finishing a Slab

Multiply length by width by thickness (in feet) to get cubic feet, divide by 27 for cubic yards, then divide by the bag yield: 0.60 cubic feet for an 80 lb bag, 0.45 for 60 lb and 0.30 for 40 lb. A 10 ft by 10 ft slab at 4 in thick is 33.3 cubic feet, or 56 bags of 80 lb mix before waste and about 62 with 10 percent extra. Pour onto a compacted base, keep the concrete moist while it cures for 5 to 7 days, and stay off it for 48 hours. Vehicles wait at least 7 days and heavy loads at least 28.

How much concrete you need, with a worked example

Bags are rated by the cubic feet of wet concrete they make, and ready-mix is sold by the cubic yard. The volume of any slab is length times width times thickness, with all three in feet, so divide the thickness in inches by 12. One cubic yard is 27 cubic feet (3 ft by 3 ft by 3 ft).

Here is the arithmetic for a 10 ft by 10 ft patio slab poured 4 in thick. Four inches is 4 divided by 12, or 0.333 ft. The volume is 10 x 10 x 0.333 = 33.3 cubic feet, which is 33.3 divided by 27 = 1.23 cubic yards.

NRMCA, the ready-mix trade association, says to order 4 percent to 10 percent more than the volume calculated from the plan dimensions, to cover contingencies. For a small hand-mixed pour we suggest the 10 percent end, because running short mid-pour can leave a cold joint, while a leftover bag costs little.

A manufacturer's data sheet for a general-purpose mix gives these yields: about 0.30 cubic feet for a 40 lb bag, 0.375 for 50 lb, 0.45 for 60 lb and 0.60 for 80 lb. Divide your volume by the yield for the bag size you plan to buy and round up. One cubic yard works out to 27 divided by 0.60 = 45 bags of 80 lb mix, which weighs 3,600 lb on its own, so a big slab is a serious hauling job.

Choosing the right product: bagged mix or ready-mix

Bagged mix is a pre-blended cement and aggregate that needs only water. The general-purpose type is rated for pours 2 in thick or more and is sold for slabs, patios, walks, steps, footings and post holes. The data sheet reports about 2,500 psi at 7 days and 4,000 psi at 28 days.

Ready-mix is made to order and arrives in a truck mixer that holds 8 to 12 cubic yards. NRMCA notes that concrete normally sets and hardens within two to eight hours after mixing, so you need the forms, helpers and tools ready before the truck arrives. Typical specified strength is 3,500 to 5,000 psi. NRMCA says concrete exposed to freezing in service should be air-entrained, so tell the producer the exposure.

The sources we read give no cutoff between bags and a truck. The limit is physical: a 1 cubic yard job is 45 bags of 80 lb mix, and each batch must be placed before it stiffens.

What to buy

Buy by category and check each item against the job.

Preparing the surface or site

Stake out the area with string and a line level, then remove sod and soil to the depth you need. The depth is the slab thickness plus the subbase, and you must allow for the width of the form lumber. For a 4 in slab on a 4 in subbase that is 8 in of excavation. A trade-association guide calls for a compacted subbase at least 4 in thick, for unstable material to be removed to a depth of at least 6 in, and says concrete must never be placed on a frozen subbase.

Tamp the subbase until it is firm. Nail the forms to stakes, backfill against them to hold them, and check the top with a level. The manufacturer's sidewalk guide recommends sloping a walk or slab away from buildings by about 1/4 in per foot, and says to check local codes and conditions.

Install expansion joint strip wherever the new concrete meets a foundation, wall or existing slab, and around posts. Support any wire mesh on small stones so it sits at the middle of the thickness. Just before the pour, dampen the subgrade without leaving puddles.

Step by step: pouring a slab

Read the bag first, because water and timing vary by product. These steps follow the manufacturer's general-purpose mix instructions.

Finishing, curing and drying times

Curing means keeping the concrete moist and warm enough for the cement to keep reacting. NRMCA says concrete in a dry environment can lose as much as 50 percent of its potential strength compared with moist-cured concrete, and recommends keeping it above 50 F. It describes the usual curing period as 3 to 7 days. The manufacturer of the bagged mix says 5 days in warm weather at 70 F or higher, or 7 days at 50 F to 70 F.

Pick one method and keep it up without gaps. A sprinkler or soaker hose must run continuously, because NRMCA says alternate wetting and drying is not acceptable. Damp burlap must stay damp. Plastic sheeting at least 4 mil thick should lie flat with taped, overlapping edges, weighted down and extending past the slab edge by at least twice its thickness. A spray-on curing compound goes on right after the water sheen disappears.

For how soon you can use the slab, the trade-association guide says normal conditions allow foot traffic after 48 hours, vehicles after at least 7 days, and heavy loads such as dumpsters or RVs after at least 28 days. The data sheet reports about 2,500 psi at 7 days and 4,000 psi at 28 days for the general-purpose bagged mix. Quick-setting and high-early-strength products list shorter times, so follow the label for those.

Common mistakes

When to hire a professional

A patio, walk or pad is a reasonable DIY job. Other work is risky or governed by rules.

Cost and ordering tips

We do not quote prices. For bags, buy one product type and bag size, add the 10 percent allowance, and compare the number of trips and the weight you must move: 62 bags of 80 lb mix is 4,960 lb.

For ready-mix, NRMCA advises ordering well ahead, having the crew ready when the truck arrives, and avoiding small clean-up loads. State the strength, the slump, the air content if the slab will freeze, and where the concrete will go.

Ask the supplier about the minimum load and short-load charge, the delivery fee, how long the truck can wait, and whether it can reach the site. Check and sign the delivery ticket. Do not add water to the load yourself: the producer cannot be responsible for concrete modified at the job site. We found no trade source that publishes a standard minimum load, so your local plant must confirm it.

Care and maintenance

NRMCA says proper curing reduces crazing, dusting and scaling. Control joints give cracks a planned place to form, so a crack along a joint is expected.

The manufacturer warns against curing compounds in late fall on surfaces that will be treated with de-icers. We found no sourced resealing interval, so follow the sealer's label.

Footings, post holes and columns

Concrete in a hole follows the same volume rule. For a round hole, volume is 3.14 times the radius squared times the depth, with all values in feet. A 12 in diameter hole has a radius of 0.5 ft, so each foot of depth holds 0.785 cubic feet. A 2.5 ft column of concrete holds about 1.96 cubic feet, which is 3.3 bags of 80 lb mix, so buy 4.

For ordinary fence posts, the manufacturer says to dig the hole about three times the diameter of the post, make its depth one third of the overall post height, place 6 in of dry mix at the bottom, plumb the post, fill, and wait 24 hours before putting the post under strain.

Structural footings are different. Residential building codes set a floor of 12 in wide and 6 in thick for a footing, with the width based on the load-bearing value of the soil, and exterior footings must go at least 12 in below the undisturbed ground surface and below the frost depth where frost protection applies. Those are minimums, so confirm frost depth and adopted code with the building department.

Pouring in cold and hot weather

Cold: NRMCA says concrete should be kept above 50 F while curing and protected from freezing until it reaches 500 psi, using insulating materials. The manufacturer of the bagged mix says to protect it from freezing for the first 48 hours, with plastic sheeting and insulating blankets if temperatures will fall below 32 F, and not to apply a curing compound if rain or temperatures below 50 F are expected within 24 hours.

Hot, dry or windy: water leaves the surface fast, which the manufacturer says can cause finishing difficulties and shrinkage cracking. NRMCA adds that concrete cured hot gains early strength quickly but ends up weaker, and that reflective plastic suits warm weather. Pour in cooler hours when possible.

How much concrete for common slab sizes

Each row uses a 4 in thickness and 10% extra. Change any number in the concrete calculator.

SlabThicknessCubic yards80 lb bags60 lb bags
10 x 10 ft slab4 in1.366282
10 x 12 ft slab4 in1.637498
12 x 12 ft slab4 in1.9689118
12 x 16 ft slab4 in2.61118157
16 x 20 ft slab4 in4.35196261
20 x 20 ft slab4 in5.43245326

Frequently asked questions

How many bags of concrete do I need for a 10x10 slab?

A 10 ft by 10 ft slab 4 in thick needs 33.3 cubic feet. That is 56 bags of 80 lb mix (0.60 cubic feet each), 75 bags of 60 lb mix (0.45 each) or 112 bags of 40 lb mix (0.30 each). Adding 10 percent for waste brings it to about 62, 82 and 123 bags.

How many 80 lb bags make a cubic yard?

A cubic yard is 27 cubic feet and an 80 lb bag of general-purpose mix yields about 0.60 cubic feet, so 27 / 0.60 = 45 bags. Check the yield printed on your bag, because different products vary.

How thick should a concrete patio or driveway be?

A trade-association guide for residential flatwork recommends at least 4 in, and at least 5 in where delivery vehicles or other heavy loads are expected. A manufacturer says sidewalks should be at least 4 in and small slabs are normally 4 in to 6 in, depending on the load. Local rules may differ, especially for driveway aprons.

How long before I can walk on new concrete?

Under normal conditions about 48 hours for foot traffic, according to a trade-association guide. The manufacturer of a general-purpose mix suggests removing forms after about 48 hours. Cold weather slows strength gain, and fast-setting products list their own times on the label.

How long before I can drive on it, or park a heavy load?

The same guide says keep vehicles off for at least 7 days, and dumpsters, RVs or heavy equipment for at least 28 days. The bagged mix data sheet reports about 2,500 psi at 7 days and 4,000 psi at 28 days.

How much water do I add to a bag of concrete?

For an 80 lb bag of general-purpose mix, start with about 6 pints (2.8 L). The final amount is typically 6 to 9 pints. For a 60 lb bag the starting figure is 4 pints, up to 7, and for a 40 lb bag 3 pints, up to 4.5. Use the least water that gives a workable, stiff mix, since extra water reduces strength.

Do I need rebar or wire mesh in a patio slab?

The manufacturer's sidewalk guide says it may be desirable to add wire mesh when using the general-purpose mix, and sells a fiber-reinforced mix that replaces mesh. It gives no firm rule, and we found no sourced requirement for rebar in a small patio. Ask your building department about driveways and anything structural.

Is bagged concrete or ready-mix better?

Bags suit small jobs, post holes and places a truck cannot reach. Ready-mix suits large placements that must be done in one continuous pour. The sources we read give no cutoff between the two, so compare the number of bags, the hauling weight and your supplier's minimum-load and short-load terms.

Can I pour concrete in cold weather?

Yes, with precautions. Do not pour on frozen ground, keep the concrete above 50 F while curing, and protect it from freezing for at least the first 48 hours. NRMCA says it should be protected from freezing until it reaches 500 psi. Avoid curing compounds if temperatures below 50 F are expected within 24 hours.

How deep should a post hole or footing be?

For a fence post the manufacturer says depth equal to one third of the post height, with the hole three times the post diameter. For structural footings, codes require at least 12 in below undisturbed ground and below frost depth where it applies, so check with your local building department.

Sources: Manufacturer data sheet: general-purpose concrete mix (yield, water, curing, slabs, posts), Manufacturer project guide: concrete sidewalks and small slabs, NRMCA CIP 31: Ordering Ready Mixed Concrete, NRMCA CIP 11: Curing In-Place Concrete, Illinois Ready Mixed Concrete Association: residential flatwork guide, Washington State residential code, WAC 51-51-0403 (footings), International Residential Code 2021, Chapter 4 Foundations (as adopted in Connecticut), OSHA: Concrete and concrete products, controlling hazards. Read 7 November 2026.

Open the concrete calculator →

What you will also need for concrete

Tools and supplies that go with this job. These are Amazon search links, so you can compare options and current prices there.

As an Amazon Associate I earn from qualifying purchases. These are paid links and cost you nothing extra.